SCHUSTER ELEMENTARY SCHOOL DROP-OFF ZONE

5515 WILL RUTH AVENUE, El Paso, TX 79924, El Paso, TX, 79924
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB3809907
$145K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 months
Duration
Registered:Mar 12, 2013
Start:May 1, 2013
Target:Jul 1, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

GRADING, HMAC PAVEMENT STRUCTURE, CONCRETE CURB AND GUTTER, CONCRETE SIDEWALKS, CHAIN LINK FENCING, PAVEMENT STR

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 12, 2013
Construction Start
May 1, 2013
Expected Completion
July 1, 2013