๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

BLINN COLLEGE TEMPORARY OVERFLOW PARKING

2703 E. VILLA MARIA, Bryan, TX 77802, Bryan, TX, 77802
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB3810021
$65K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3 months
Duration
Registered:Mar 13, 2013
Start:Apr 1, 2013
Target:Jul 1, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Parking lot and pedestrian access to campus

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 13, 2013
Construction Start
April 1, 2013
Expected Completion
July 1, 2013