๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CASTLEBERRY ISD ADM-BLDG RENO SHELL PKG

5228 OHIO GARDEN ROAD, Fort Worth, TX 76114, Fort Worth, TX, 76114
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4801460
$600K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Sep 26, 2013
Start:Nov 1, 2013
Target:Mar 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Project includes new exterior surfacing on existing concrete walls, new exterior doors and window, new electrica

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 26, 2013
Construction Start
November 1, 2013