โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

FIRST BAPTIST CHURCH BOY SCOUT ADDITION

3015 MOORES LANE, Texarkana, TX 75503, Texarkana, TX, 75503
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4810993
$172K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7 months
Duration
Registered:Mar 13, 2014
Start:Mar 1, 2014
Target:Oct 1, 2014
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Slab-on-grade, wood framing, shingle roof, wood siding,interior drywall.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 13, 2014
Construction Start
March 1, 2014
Expected Completion
October 1, 2014