๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FRENCH ELEMENTARY SCHOOL

5802 W RAYFORD RD, Spring, TX 77389, Spring, TX, 77389
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4811313
$17.2M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1 year
Duration
Registered:Mar 18, 2014
Start:Jun 1, 2014
Target:Jun 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New 125,000 square foot elementary school with academicinstruction areas, media center, art, science and music

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 18, 2014
Construction Start
June 1, 2014
Expected Completion
June 1, 2015