๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

LAKEWAY BAPTIST CHURCH ADDITION

5801 FM 1960 EAST, Humble, TX 77346, Humble, TX, 77346
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5800093
$750K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
11 months
Duration
Registered:Sep 3, 2014
Start:Oct 1, 2014
Target:Sep 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

2,859 SF consisting of addition to existing sanctuary, expanded foyer, and new restrooms. Sitework to include ad

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 3, 2014
Construction Start
October 1, 2014
Expected Completion
September 1, 2015