๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

WAL-MART MARKET AND FUEL STATION #4454

S. CENTRAL BLVD & LOUIS RITTER, Red Oak, TX 75154, Red Oak, TX, 75154
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5805555
$3.3M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3y 1mo
Duration
Registered:Nov 25, 2014
Start:Feb 1, 2015
Target:Feb 1, 2018
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

new construction of Wal Mart Market and Fuel Station

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 25, 2014
Construction Start
February 1, 2015
Expected Completion
February 1, 2018