๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
CORNERSTONE BUILDING NO. 3 REVISED
8562 NW LOOP 410, San Antonio, TX 78210, San Antonio, TX, 78210
Completed100%
๐Project Metrics
TDLR #EABPRJB5807158$5.6M
Project Value
โ
Square Feet
โ
Cost/SqFt
9 months
Duration
Registered:Dec 24, 2014
Start:Jan 1, 2015
Target:Oct 1, 2015
๐
Project Closed
Project has been completed and closed
๐Scope of Work
A new 144,137 s.f. warehouse building including site improvements
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 24, 2014
Construction Start
January 1, 2015
Expected Completion
October 1, 2015
๐Related Projects
๐คSame Owner
$2.5M totalProperty Owner
๐ค
AREA REAL ESTATE LLC
4 projects ยท $2.5M
View all projects
DAVID M. ADELMAN 1221 BROADWAY, SUITE 104, SAN ANTONIO, TX 78215
Design Firm
๐๏ธ
PSRBB INDUSTRIAL GROUP INC.
4 projects ยท $666K
View all projects
H. THOMAS PRESTIDGE 1845 NORTHWESTERN DR., SUITE A, EL PASO, TX 79912