๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MISD 2012 BOND - DEZAVALA RENOVATIONS

705 N. LEE STREET, Midland, TX 79701, Midland, TX, 79701
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5807628
$300K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
10 months
Duration
Registered:Jan 6, 2015
Start:Feb 1, 2015
Target:Dec 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovate exterior drive lanes & utility service. Minorinterior renovations to main entry. Add single accessib

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 6, 2015
Construction Start
February 1, 2015
Expected Completion
December 1, 2015