๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

STP 2015 (163)

VARIOUS HIGHWAYS, San Angelo, TX 76901, San Angelo, TX, 76901
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5811856
$410K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
8 months
Duration
Registered:Mar 16, 2015
Start:Dec 1, 2015
Target:Aug 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Upgrade traffic signals and illumination in Tom Green County; including curb ramps, crosswalks, and pedestrian t

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 16, 2015
Construction Start
December 1, 2015
Expected Completion
August 1, 2016