🏁Project Closed🔧 Additions to Existing Building💵 This project involves public funds, public land, or is a Federally funded roadway project.
HARTLEY SCHOOL RENOVATIONS AND ADDITIONS
9TH AND JOHNSON, Hartley, TX 79044, Hartley, TX, 79044
Completed100%
📊Project Metrics
TDLR #EABPRJB5812154$5.7M
Project Value
—
Square Feet
—
Cost/SqFt
1y 4mo
Duration
Registered:Mar 20, 2015
Start:Jun 1, 2015
Target:Oct 1, 2016
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
New gym, classrooms, library, commons, restrooms attached to the existing school buildings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
March 20, 2015
Construction Start
June 1, 2015
Expected Completion
October 1, 2016