HARTLEY SCHOOL RENOVATIONS AND ADDITIONS

9TH AND JOHNSON, Hartley, TX 79044, Hartley, TX, 79044
Completed100%

📊Project Metrics

TDLR #EABPRJB5812154
$5.7M
Project Value
Square Feet
Cost/SqFt
1y 4mo
Duration
Registered:Mar 20, 2015
Start:Jun 1, 2015
Target:Oct 1, 2016
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

New gym, classrooms, library, commons, restrooms attached to the existing school buildings.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
March 20, 2015
Construction Start
June 1, 2015
Expected Completion
October 1, 2016