๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

OUR LADY OF GRACE ACTIVITY CENTER ADD

223 E. SUMMIT, San Antonio, TX 78213, San Antonio, TX, 78213
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5813625
$1.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
8 months
Duration
Registered:Apr 13, 2015
Start:May 1, 2015
Target:Jan 1, 2016
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Add meeting rooms to the existing activity center.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 13, 2015
Construction Start
May 1, 2015
Expected Completion
January 1, 2016