πProject ClosedποΈ New Construction
RM 1111 DRAW BRIDGE REPLACEMENT
Completed100%
πProject Metrics
TDLR #EABPRJB5816562$2.0M
Project Value
β
Square Feet
β
Cost/SqFt
6 months
Duration
Registered:May 26, 2015
Start:Oct 1, 2015
Target:Apr 1, 2016
π
Project Closed
Project has been completed and closed
π Compliance Timeline
Project Registered
May 26, 2015
Construction Start
October 1, 2015
Expected Completion
April 1, 2016