๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

FUEL CITY

1715 HALTOM CITY, Haltom City, TX 76117, Haltom City, TX, 76117
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6810346
$3.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
6 months
Duration
Registered:Feb 18, 2016
Start:Mar 1, 2016
Target:Sep 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Retail facilty with fuel

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 18, 2016
Construction Start
March 1, 2016
Expected Completion
September 1, 2016