โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CITY OF FORT WORTH FIRE STATION 42

450 E. RENDON CROWLEY RD., Fort Worth, TX 76028, Fort Worth, TX, 76028
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6815719
$4.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 2mo
Duration
Registered:May 4, 2016
Start:Jul 1, 2016
Target:Sep 1, 2017
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Provide a new fire station facility for the City of FortWorth.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 4, 2016
Construction Start
July 1, 2016
Expected Completion
September 1, 2017