๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
FM 389 REHABILITATION
W. OF FM 332 TO US 290, Brenham, TX 77833, Brenham, TX, 77833
Completed100%
๐Project Metrics
TDLR #EABPRJB6815868$302K
Project Value
โ
Square Feet
โ
Cost/SqFt
3y 3mo
Duration
Registered:May 5, 2016
Start:Jul 1, 2016
Target:Aug 31, 2019
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Rehabilitate existing roadway consisting of grading, structures, base, surface, signs and pavement markings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 5, 2016
Construction Start
July 1, 2016
Expected Completion
August 31, 2019
๐Related Projects
๐คSame Owner
$6.5M total๐๏ธSame Design Firm
$18.3M totalProperty Owner
๐ค
TXDOT DISTRICT: BRYAN
4 projects ยท $6.5M
View all projects
2591 N. EARL RUDDER FREEWAY _, BRYAN, TEXAS 77803
Design Firm
๐๏ธ
TEXAS DEPARTMENT OF TRANSPORTATION
4 projects ยท $18.3M
View all projects
ROBIN HANDEL, P.E. 2591 N. EARL RUDDER FREEWAY, BRYAN, TX 77803