๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

TAKE 5 OIL CHANGE

651 ALTA MERE DRIVE, Fort Worth, TX 76114, Fort Worth, TX, 76114
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6821659
$286K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3 months
Duration
Registered:Jul 29, 2016
Start:Sep 1, 2016
Target:Dec 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construct a 3 bay oil changing facility. Customers remain in vehicle while oil change is being completed. Wood

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 29, 2016
Construction Start
September 1, 2016
Expected Completion
December 1, 2016