๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

INNOVATION CENTER

1050 BRIDGEWOOD DRIVE, Fort Worth, TX 76112, Fort Worth, TX, 76112
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7807535
$5.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
9 months
Duration
Registered:Dec 27, 2016
Start:Mar 1, 2017
Target:Dec 1, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

56,000 existing big box space converted into a new training/data center.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 27, 2016
Construction Start
March 1, 2017
Expected Completion
December 1, 2017