๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
WBS NO. N-320668-0037-3 WOOLWORTH SIDEWA
BETWEEN COLFAX ST AND Wallisville Rd., Houston, TX 77020, Houston, TX, 77020
Construction50%
๐Project Metrics
TDLR #EABPRJB8801987$186K
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 8mo
Duration
Registered:Oct 3, 2017
Start:Oct 1, 2017
Target:May 15, 2019
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of new 5 foot wide sidewalk to include pedestrian ramps at intersections.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 3, 2017
Construction Start
October 1, 2017
Expected Completion
May 15, 2019
๐Related Projects
๐คSame Owner
$29.6M totalProperty Owner
๐ค
CITY OF HOUSTON
4 projects ยท $29.6M
View all projects
SAM KANU P.E. 611 WALKER ST., 14TH FLOOR, HOUSTON, TX 77002
Design Firm
๐๏ธ
AIA ENGINEERS LTD.
4 projects ยท $3.1M
View all projects
SANDEEP PATIL P.E. 15310 PARK ROW, HOUSTON, TX 77084