๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
FM 2493
FROM FM 2813 TO S OF FM 346, Tyler, TX 75703, Tyler, TX, 75703
Completed100%
๐Project Metrics
TDLR #EABPRJB8814481$13.3M
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 10mo
Duration
Registered:Apr 11, 2018
Start:Oct 1, 2018
Target:Aug 1, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Grading, Flex Base, ASPH Pavement, C&G, Culvert extension, storm drain, signing and pavement markings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 11, 2018
Construction Start
October 1, 2018
Expected Completion
August 1, 2020
๐Related Projects
๐คSame Owner
$20.2M totalProperty Owner
๐ค
TXDOT DISTRICT: TYLER
4 projects ยท $20.2M
View all projects
_ 2709 W FRONT ST, TYLER, TEXAS 75702