Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8819412
$200K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Jun 13, 2018
Start:Jul 1, 2018
Target:Dec 1, 2018
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

CMU Utility Building, equipment foundations, gravel andpaved drives, and site grading improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 13, 2018
Project Closed
December 1, 2018
Construction Start
July 1, 2018
Expected Completion
December 1, 2018