โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

CITY OF FARMERS BRANCH CAMELOT LANDFILL

TO BE DETERMINED, Farmers Branch, TX 75056, Farmers Branch, TX, 75056
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB9803584
$2.9M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
8 months
Duration
Registered:Oct 23, 2018
Start:Nov 1, 2018
Target:Jul 1, 2019
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Work consist of a Maintenance Shop, Office and a Scale House

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 23, 2018
Construction Start
November 1, 2018
Expected Completion
July 1, 2019