๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Band Hall Additions and Improvements
100 Rebel Road, Ore City, TX 75683, Ore City, TX, 75683
Completed100%
๐Project Metrics
TDLR #TABS2019007191$1.5M
Project Value
8,037
Square Feet
$187/sqft
Cost/SqFt
10 months
Duration
Registered:Mar 18, 2019
Start:May 25, 2019
Target:Mar 31, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
The project consists of the additions (4,903 sf of new construction) and improvements to the existing Band Hall (3,134 sf existing) as outlined on the construction documents.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 18, 2019
Construction Start
May 25, 2019
Expected Completion
March 31, 2020
๐Related Projects
Property Owner
๐ค
ORE CITY INDEPENDENT SCHOOL DISTRICT
View company profile
100 Rebel Road, Ore City, Texas 75683
Design Firm
๐๏ธ
Thacker | Davis Architects, Inc.
4 projects ยท $2.7M
View all projects
1100 Judson Road Suite 620, Longview, Texas 75601