Beechnut Rd Paving and Drainage Improvements

Beechnut Rd, Richmond, TX 77407, Richmond, TX, 77407
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019008171
$5.2M
Project Value
380,000
Square Feet
$14/sqft
Cost/SqFt
10 months
Duration
Registered:Mar 29, 2019
Start:Aug 1, 2019
Target:Jun 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

4-lane concrete boulevard with curb and gutter will be built to replace existing 2-lane asphalt road from NETCO Pipeline to Fm 1464. Sidewalk will be built on one side (north side). Roadway design will include traffic signal at Westmoor intersection.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 29, 2019
Construction Start
August 1, 2019
Expected Completion
June 1, 2020