๐Review Complete๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
Williams Memorial Methodist Church Columbarium
4000 Moores Lane, Texarkana, TX 75503, Texarkana, TX, 75503
Construction50%
๐Project Metrics
TDLR #TABS2020006121$15.0M
Project Value
3,500
Square Feet
$4.29K/sqft
Cost/SqFt
5 months
Duration
Registered:Nov 22, 2019
Start:Dec 1, 2019
Target:May 1, 2020
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of a concrete plaza. Approx. 35' x 45" w/ (3) Masonry walls used to house ashes of the deceased. Access will be from sanctuary of church & an adjacent asphalt walking trail.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 22, 2019
Review Complete
November 22, 2019
Construction Start
December 1, 2019
Expected Completion
May 1, 2020
๐Related Projects
๐Nearby Projects
Within 1 kmProperty Owner
๐ค
Williams Memorial Church
Contact: Tom Hughes
View company profile
4000 Moores Lane, Texarkana, Texas 75503
Design Firm
๐๏ธ
Cox Exterior Design & Development
View company profile
560 Myrtle Springs Rd., Texarkana, Texas 75503