โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FWISD - Polytechnical High School - Master Site

1300 Conner Avenue, Fort Worth, TX 76105, Fort Worth, TX, 76105
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020007377
$2.0M
Project Value
82,764
Square Feet
$24/sqft
Cost/SqFt
2y 2mo
Duration
Registered:Dec 13, 2019
Start:Mar 9, 2020
Target:Apr 27, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Package consists of demolition of existing site paving and utilities for school campus. Installation of new infrastructure underground utilities and re-grading of site for future addition buildings.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 13, 2019
Construction Start
March 9, 2020
Expected Completion
April 27, 2022