Project intelligenceTDLR TABS2020011503Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Los Fresnos CISD Add and Reno at Resaca Middle School

33422 FM 1575, Los Fresnos, TX, 78566

Construction complete · Mar 2021Project Closed

Los Fresnos CISD Add and Reno at Resaca Middle School is a renovation/alteration project at 33422 FM 1575, Los Fresnos, in Cameron County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2021). The project has an estimated value of $900K across about 4,000 sq ft.

Estimated project value
$900K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
4,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$225/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Feb 13, 2020412 days across supplied datesMar 31, 2021

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    47 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    365 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78566 (Los Fresnos)

One email per change. Unsubscribe in one click. Privacy.

Los Fresnos CISD Add and Reno at Resaca Middle School is a Renovation/Alteration project located at 33422 FM 1575, Los Fresnos, TX 78566 in Los Fresnos, Texas. The project has an estimated value of $900K covering 4,000 sq ft. Los Fresnos Cons. Ind. School District is the property owner and Gomez Mendez Saenz, Inc. is the design firm of record. The project was registered with TDLR on February 13, 2020.

Frequently Asked Questions

What is Los Fresnos CISD Add and Reno at Resaca Middle School?

Los Fresnos CISD Add and Reno at Resaca Middle School is a renovation/alteration project at 33422 FM 1575 in Los Fresnos, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Additions and Renovations

Is Los Fresnos CISD Add and Reno at Resaca Middle School open in Los Fresnos?

Construction on Los Fresnos CISD Add and Reno at Resaca Middle School is complete — TDLR records show the project passed its required accessibility inspection in Mar 2021. The building is finished and very likely open.

Where is Los Fresnos CISD Add and Reno at Resaca Middle School located?

Los Fresnos CISD Add and Reno at Resaca Middle School is located at 33422 FM 1575, Los Fresnos, TX, 78566, in Cameron County.

Who is the owner or developer of Los Fresnos CISD Add and Reno at Resaca Middle School?

Los Fresnos Cons. Ind. School District is the property owner/developer of record for Los Fresnos CISD Add and Reno at Resaca Middle School, per its TDLR project registration.

Who is the architect or design firm for Los Fresnos CISD Add and Reno at Resaca Middle School?

Gomez Mendez Saenz, Inc. is the design firm of record for Los Fresnos CISD Add and Reno at Resaca Middle School, according to its TDLR filing.

How much does Los Fresnos CISD Add and Reno at Resaca Middle School cost and how big is it?

Los Fresnos CISD Add and Reno at Resaca Middle School has an estimated construction value of $900K and approximately 4,000 square feet (about $225/sqft), based on its TDLR filing.

Scope of Work

Additions and Renovations

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

33422 FM 1575, Los Fresnos, TX, 78566

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78566 (Los Fresnos)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Los Fresnos?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.