Funding type
This project involves public funds, public land, or is a Federally funded roadway project.
Lakeside City Community Center and Fire Hall in Wichita Falls, TX
4344 State Hwy 79, Wichita Falls, TX, 76310
Lakeside City Community Center and Fire Hall is a new construction project at 4344 State Hwy 79, Wichita Falls, in Archer County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2021). The project has an estimated value of $1.3M across about 9,875 sq ft.
- Estimated project value
- $1.3M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 9,875 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $127/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 1 year
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
30 days after the preceding date shown.
Source: TDLR filing
View source recordProject closed · TDLR filing
The project record was closed in TDLR.
365 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
Same day as the preceding date shown.
Source: TDLR filing
View source record
Project Closed
Project has been completed and closed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 76310 (Wichita Falls)
One email per change. Unsubscribe in one click. Privacy.
Lakeside City Community Center and Fire Hall is a New Construction project located at 4344 State Hwy 79, Wichita Falls, TX 76310 in Wichita Falls, Texas. The project has an estimated value of $1.3M covering 9,875 sq ft. LAKESIDE CITY - MAYOR CORY GLASSBURN is the property owner and HARPER PERKINS ARCHITECTS is the design firm of record. The project was registered with TDLR on February 14, 2020.
Frequently Asked Questions
What is Lakeside City Community Center and Fire Hall?
Lakeside City Community Center and Fire Hall is a new construction project at 4344 State Hwy 79 in Wichita Falls, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Project will be a new construction community center, administration office and fire truck storage facility.
Is Lakeside City Community Center and Fire Hall open in Wichita Falls?
Construction on Lakeside City Community Center and Fire Hall is complete — TDLR records show the project passed its required accessibility inspection in Mar 2021. The building is finished and very likely open.
Where is Lakeside City Community Center and Fire Hall located?
Lakeside City Community Center and Fire Hall is located at 4344 State Hwy 79, Wichita Falls, TX, 76310, in Archer County.
Who is the owner or developer of Lakeside City Community Center and Fire Hall?
LAKESIDE CITY - MAYOR CORY GLASSBURN is the property owner/developer of record for Lakeside City Community Center and Fire Hall, per its TDLR project registration.
Who is the architect or design firm for Lakeside City Community Center and Fire Hall?
HARPER PERKINS ARCHITECTS is the design firm of record for Lakeside City Community Center and Fire Hall, according to its TDLR filing.
How much does Lakeside City Community Center and Fire Hall cost and how big is it?
Lakeside City Community Center and Fire Hall has an estimated construction value of $1.3M and approximately 9,875 square feet (about $127/sqft), based on its TDLR filing.
Scope of Work
Project will be a new construction community center, administration office and fire truck storage facility.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
4344 State Hwy 79, Wichita Falls, TX, 76310
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Watch all construction in 76310 (Wichita Falls)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Wichita Falls?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.