Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Widening Non-Freeway at FM 2818
CSJ: 2399-01-074, etc., College Station, TX 77845, College Station, TX, 77845
Final Inspection85%
๐Project Metrics
TDLR #TABS2020012585$47.3M
Project Value
232,791
Square Feet
$203/sqft
Cost/SqFt
4 years
Duration
Registered:Feb 28, 2020
Start:Sep 1, 2020
Target:Aug 7, 2024
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Construction of grading, road base, structure, concrete median barrier, Share-Use Path, curb ramp, traffic signal for pedestrian and vehicle,cross walk, and Etc.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 28, 2020
Construction Start
September 1, 2020
Expected Completion
August 7, 2024
๐Related Projects
๐คSame Owner
$13.6M totalProperty Owner
๐ค
TxDOT District: Bryan
Contact: Ashley Hill, P.E.
4 projects ยท $13.6M
View company profile
2591 North Earl Rudder Freeway, Bryan, Texas 77803
Design Firm
๐๏ธ
Binkley & Barfield, Inc.
4 projects ยท $38.3M
View company profile
1710 Seamist Dr, Houston, Texas 77008