๐Project Closed๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
2019 Marion ISD Bond Projects Pkg 2
211 West Otto St., Marion, TX 78124, Marion, TX, 78124
Completed100%
๐Project Metrics
TDLR #TABS2020014834$15.9M
Project Value
32,000
Square Feet
$497/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Apr 1, 2020
Start:Mar 2, 2020
Target:Aug 2, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Krueger Primary Campus: Ren of extg Gym structure, extg Cafet, and Library. Add of new Kitchen, Pre-K academic wing, and outdoor covered pavilion for PE. Incl site work. HS: clsrm addi of science labs and gen clsrms. East campus add of CTE shop/tr
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 1, 2020
Construction Start
March 2, 2020
Expected Completion
August 2, 2021