๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Deaf Smith County Jail and Sheriff's Office

3782 N. Progressive Rd. and 3780 N. Progressive Rd, Hereford, TX 79045, Hereford, TX, 79045
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020019210
$32.0M
Project Value
166,345
Square Feet
$192/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Jun 18, 2020
Start:Aug 1, 2020
Target:Feb 28, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of new jail and Sheriff's office. This project will be approximately 83,173 square feet (Sheriffโ€™s office is 14,804 square feet, the jail is 58,385 square feet and the sallyport/covered parking area is 9,984 square feet).

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 18, 2020
Project Closed
February 28, 2022
Construction Start
August 1, 2020
Expected Completion
February 28, 2022

Get alerts for Deaf Smith

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists