๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Anna Crossing Phase 1C

Powell Parkway and Finley Road, Anna, TX 75409, Anna, TX, 75409
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020019774
$2.8M
Project Value
49,433
Square Feet
$56/sqft
Cost/SqFt
9 months
Duration
Registered:Jun 29, 2020
Start:Jul 1, 2020
Target:Apr 1, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Land Development for 102 residential lots.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 29, 2020
Construction Start
July 1, 2020
Expected Completion
April 1, 2021