Inspection Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.

Bexar Co. ESD 12 FS 136

11800 E US Hwy 87, Adkins, TX 78101, Adkins, TX, 78101
Final Inspection85%

📊Project Metrics

TDLR #TABS2020020099
$2.3M
Project Value
9,825
Square Feet
$229/sqft
Cost/SqFt
11 months
Duration
Registered:Jul 6, 2020
Start:Feb 9, 2022
Target:Dec 29, 2022

Inspection Complete

Final inspection completed, awaiting project closure

📋Scope of Work

Construction of New Fire Station and Related Site Work

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
July 6, 2020
Construction Start
February 9, 2022
Expected Completion
December 29, 2022