๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

New Motor Bank

600 Pat Booker Road, Universal City, TX 78148, Universal City, TX, 78148
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020020827
$250K
Project Value
600
Square Feet
$417/sqft
Cost/SqFt
5 months
Duration
Registered:Jul 20, 2020
Start:Sep 1, 2020
Target:Feb 1, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New two lane motor bank for texstar national bank

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 20, 2020
Construction Start
September 1, 2020
Expected Completion
February 1, 2021