πProject ClosedποΈ New Construction
VGXI - New Biomanufacturing Facility
Completed100%
πProject Metrics
TDLR #TABS2021004657$57.0M
Project Value
β
Square Feet
β
Cost/SqFt
11 months
Duration
Registered:Nov 19, 2020
Start:Jan 20, 2021
Target:Dec 30, 2021
π
Project Closed
Project has been completed and closed
VGXI - New Biomanufacturing Facility is a New Construction project in Texas. The project has an estimated value of $57.0M.. The project was registered with TDLR on November 19, 2020.
π Compliance Timeline
Project Registered
November 19, 2020
Project Closed
December 30, 2021
Construction Start
January 20, 2021
Expected Completion
December 30, 2021
π Project Timeline
Filed
Nov 19, 2020
Review Complete
Inspection Complete
Closed
Dec 30, 2021
Explore Area
Need a contractor for this project?
Browse verified general contractors active in Mills County