πProject ClosedποΈ New Construction
City of Cactus - Municipal Aquatic Center
Completed100%
πProject Metrics
TDLR #TABS2021009019$2.8M
Project Value
β
Square Feet
β
Cost/SqFt
11 months
Duration
Registered:Feb 8, 2021
Start:May 24, 2021
Target:Apr 18, 2022
π
Project Closed
Project has been completed and closed
City of Cactus - Municipal Aquatic Center is a New Construction project in Texas. The project has an estimated value of $2.8M.. The project was registered with TDLR on February 8, 2021.
π Compliance Timeline
Project Registered
February 8, 2021
Project Closed
April 18, 2022
Construction Start
May 24, 2021
Expected Completion
April 18, 2022
π Project Timeline
Filed
Feb 8, 2021
Review Complete
Inspection Complete
Closed
Apr 18, 2022
Explore Area
Need a contractor for this project?
Browse verified general contractors active in Mitchell County
Find General Contractors in Mitchell