Project intelligenceTDLR TABS2021010633New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Pyburn Elementary School Replacement in Houston, TX

12302 Coulson Street, Houston, TX, 77015

Construction complete · Jul 2023Project Closed

Pyburn Elementary School Replacement is a new construction project at 12302 Coulson Street, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jul 2023). The project has an estimated value of $23.0M across about 104,000 sq ft.

Estimated project value
$23.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
104,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$221/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 1mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Mar 8, 2021847 days across supplied datesJul 3, 2023

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    85 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    762 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77015 (Houston)

One email per change. Unsubscribe in one click. Privacy.

Pyburn Elementary School Replacement is a New Construction project located at 12302 Coulson Street, Houston, TX 77015 in Houston, Texas. The project has an estimated value of $23.0M covering 104,000 sq ft. Galena Park ISD is the property owner and S. Chu Architects, Inc. is the design firm of record. The project was registered with TDLR on March 8, 2021.

Frequently Asked Questions

What is Pyburn Elementary School Replacement?

Pyburn Elementary School Replacement is a new construction project at 12302 Coulson Street in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construct a new elementary school to replace the existing elementary on the same site

Is Pyburn Elementary School Replacement open in Houston?

Construction on Pyburn Elementary School Replacement is complete — TDLR records show the project passed its required accessibility inspection in Jul 2023. The building is finished and very likely open.

Where is Pyburn Elementary School Replacement located?

Pyburn Elementary School Replacement is located at 12302 Coulson Street, Houston, TX, 77015, in Harris County.

Who is the owner or developer of Pyburn Elementary School Replacement?

Galena Park ISD is the property owner/developer of record for Pyburn Elementary School Replacement, per its TDLR project registration.

Who is the architect or design firm for Pyburn Elementary School Replacement?

S. Chu Architects, Inc. is the design firm of record for Pyburn Elementary School Replacement, according to its TDLR filing.

How much does Pyburn Elementary School Replacement cost and how big is it?

Pyburn Elementary School Replacement has an estimated construction value of $23.0M and approximately 104,000 square feet (about $221/sqft), based on its TDLR filing.

Scope of Work

Construct a new elementary school to replace the existing elementary on the same site

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

12302 Coulson Street, Houston, TX, 77015

Location by street address

Watch all construction in 77015 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.