โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Cibolo City Hall Annex

201 West Loop 539, Cibolo, TX 78108, Cibolo, TX, 78108
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021016547
$2.1M
Project Value
10,000
Square Feet
$210/sqft
Cost/SqFt
9 months
Duration
Registered:May 27, 2021
Start:Jun 15, 2021
Target:Mar 18, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Remodel and addition to the Old Cibolo Schoolhouse.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 27, 2021
Construction Start
June 15, 2021
Expected Completion
March 18, 2022