โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

St. Austin Redevelopment - Parish

2026 Guadalupe St, Austin, TX 78705, Austin, TX, 78705
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021019367
$16.2M
Project Value
77,478
Square Feet
$208/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Jul 8, 2021
Start:Sep 1, 2021
Target:Apr 19, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

5 story private PK-8th grade school, administrative offices.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 8, 2021
Construction Start
September 1, 2021
Expected Completion
April 19, 2023

๐Ÿ“„Related City Permits

Building permits found at or near this location

2026 GUADALUPE ST

ePlan-Expedited Review: New Construction of an aerial walkway to connect two adjacent buildings (191 SF).

FinalElectrical PermitNewJan 2025
View Details
2023-133180 EP
๐Ÿ”งBergelectric Corporation
2026 GUADALUPE ST

ePlan-Expedited Review: New Construction of an aerial walkway to connect two adjacent buildings (191 SF).

FinalBuilding PermitNewJan 2025
$4K
View Details
2023-133180 BP
๐Ÿ”งHensel Phelps Construction Co. ***MAIN***
2026 NORTHRIDGE DR

Coy - Install new 10.95kW rooftop solar system to existing residential only using line side tap

FinalElectrical PermitAuxiliary PowerFeb 2024
View Details
2024-013332 EP
2026 NORTHRIDGE DR

Coy Upgrade - Disconnect/reconnect power to tie in PV component and upgrading MSP to 200 Amps. Upgrading revenue meter to 200 Amps

FinalElectrical PermitUpgradeFeb 2024
View Details
2024-013374 EP
2026 GUADALUPE ST

***All work to take place behind existing closures Permit #2022 110758 RW NO WORK TO OCCUR AFTER 07/31/23 - UNTIL RW IS EXTENDED*** ***PER COORDINATION WITH 2022-114191 EX NO WORK TO OCCUR AFTER 08/01/23 WITHOUT ADDITIONAL COORDINATION*** Construct new 65 LF of sidewalk and curb & gutter of 126 LF. Shall meet all city standards. **ki INSPECTION FEES PAID ON SSI 2022 074727

FinalDriveway / SidewalksNewJul 2023
View Details
2023-029418 DS