Reeves County ESD 1 & 2- Fire/EMS Station #2 in Orla, TX

U.S. 285 & County Road 433, Orla, TX, 79770

Construction complete · Sep 2026Inspection Complete

Reeves County ESD 1 & 2- Fire/EMS Station #2 is a new construction project at U.S. 285 & County Road 433, Orla, in Reeves County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $9.0M across about 16,570 sq ft.

Estimated project value
$9.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
16,570 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$543/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
4y 10mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 31, 20211,845 days across supplied datesSep 19, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    91 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    1,735 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    19 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Reeves County ESD 1 & 2- Fire/EMS Station #2

The Reeves County ESD 1 & 2 - Fire/EMS Station #2 in Orla is a completed 16,570 sq ft facility located at U.S. 285 & County Road 433. This new construction project, valued at $9,000,000, passed its final TDLR accessibility inspection in September 2026. The building is designed to serve the local emergency services community with a comprehensive layout for fire and EMS operations.

Martinez Architects served as the design firm of record for this project, which is part of a broader investment in emergency infrastructure by Reeves County Emergency Services Districts No. 1 and No. 2. The district also manages two other TDLR-registered stations in the region, including facilities in Pecos and Balmorhea. The Orla station represents a significant addition to the district’s capabilities, with an estimated cost per square foot of $543.

Project Scope and Financials

The filing for this project identifies it as a new Fire/EMS Station, a critical component of the county's emergency response network. With a total estimated cost of $9,000,000, the project exceeds the median estimated cost of $2,482,000 for similar new construction filings in Reeves County. The scheduled build window of 1,735 days was longer than the county median of 365 days, reflecting the complexity and scale of the facility.

Construction began in November 2021, following the completion of plan review in August 2021. The project was registered with the Texas Department of Licensing and Regulation in August 2021. The final inspection was passed in September 2026, marking the successful conclusion of the construction phase. The project involves public funds and public land, ensuring that the facility meets all necessary state and federal standards for accessibility and safety.

Regional Context

Reeves County has seen a steady increase in infrastructure projects, with 13 new construction filings registered in the last 24 months. The Reeves County ESD 1 & 2 - Fire/EMS Station #2 stands out as one of the larger and more significant projects in the area. The local labor market, with an unemployment rate of 4.1 percent in July 2026, reflects a stable economic environment that supports such large-scale public works.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79770 (Orla)

One email per change. Unsubscribe in one click. Privacy.

Reeves County ESD 1 & 2- Fire/EMS Station #2 is a New Construction project located at U.S. 285 & County Road 433, Orla, TX 79770 in Orla, Texas. The project has an estimated value of $9.0M covering 16,570 sq ft. Reeves County Emergency Services Districts No. 1 and No. 2 is the property owner and Martinez Architects is the design firm of record. The project was registered with TDLR on August 31, 2021.

Frequently Asked Questions

Is the Reeves County ESD 1 & 2 - Fire/EMS Station #2 open for business?

The construction is complete, and the building passed its final TDLR accessibility inspection in September 2026. The TDLR record confirms the construction status, but does not specify the exact date the facility began operations.

Who designed the Reeves County ESD 1 & 2 - Fire/EMS Station #2?

Martinez Architects was the design firm of record for this project. They were responsible for the architectural plans that guided the construction of the 16,570 sq ft facility.

What is the total cost of the Reeves County ESD 1 & 2 - Fire/EMS Station #2?

The estimated cost for this project is $9,000,000. This figure is above the median estimated cost for new construction projects in Reeves County, reflecting the facility's size and scope.

When did construction begin on the Reeves County ESD 1 & 2 - Fire/EMS Station #2?

Construction started in November 2021, following the completion of plan review in August 2021. The project was registered with TDLR in August 2021.

What is the size of the Reeves County ESD 1 & 2 - Fire/EMS Station #2?

The facility is 16,570 sq ft. This size is slightly above the median size of 13,738 sq ft for new construction projects in Reeves County.

What is Reeves County ESD 1 & 2- Fire/EMS Station #2?

Reeves County ESD 1 & 2- Fire/EMS Station #2 is a new construction project at U.S. 285 & County Road 433 in Orla, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New Fire/EMS Station

Is Reeves County ESD 1 & 2- Fire/EMS Station #2 open in Orla?

Construction on Reeves County ESD 1 & 2- Fire/EMS Station #2 is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is Reeves County ESD 1 & 2- Fire/EMS Station #2 located?

Reeves County ESD 1 & 2- Fire/EMS Station #2 is located at U.S. 285 & County Road 433, Orla, TX, 79770, in Reeves County.

Who is the owner or developer of Reeves County ESD 1 & 2- Fire/EMS Station #2?

Reeves County Emergency Services Districts No. 1 and No. 2 is the property owner/developer of record for Reeves County ESD 1 & 2- Fire/EMS Station #2, per its TDLR project registration.

Who is the architect or design firm for Reeves County ESD 1 & 2- Fire/EMS Station #2?

Martinez Architects is the design firm of record for Reeves County ESD 1 & 2- Fire/EMS Station #2, according to its TDLR filing.

How much does Reeves County ESD 1 & 2- Fire/EMS Station #2 cost and how big is it?

Reeves County ESD 1 & 2- Fire/EMS Station #2 has an estimated construction value of $9.0M and approximately 16,570 square feet (about $543/sqft), based on its TDLR filing.

Scope of Work

New Fire/EMS Station

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

U.S. 285 & County Road 433, Orla, TX, 79770

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 79770 (Orla)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.