Project intelligenceTDLR TABS2022000821New Construction
Funding type

This project is privately funded, on private land for private use.

CEFCO CONVENIENCE STORES # 1112

677 E. NORTHEAST LOOP 323 AT F M 14, Tyler, TX, 75708

Construction complete · May 2023Project Closed

CEFCO CONVENIENCE STORES # 1112 is a new construction project at 677 E. NORTHEAST LOOP 323 AT F M 14, Tyler, in Smith County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed May 2023). The project has an estimated value of $833K across about 6,000 sq ft.

Estimated project value
$833K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
6,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$139/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 3mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Sep 13, 2021595 days across supplied datesMay 1, 2023

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    141 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    454 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

📰About CEFCO CONVENIENCE STORES # 1112

Cefco Convenience Stores # 1112 is a new gas station located at 677 E. NORTHEAST LOOP 323 AT F M 14 in Tyler, Texas. The project, registered with the Texas Department of Licensing and Regulation (TDLR), encompasses 6,000 square feet of new construction. The estimated cost for this build is $832,600, resulting in a cost of $139 per square foot.

The project was filed in September 2021, with construction beginning in February 2022. The scheduled completion date on the filing was May 2023. TDLR closed the project file in May 2023, which marks the end of the accessibility review process for this construction. This status indicates that the regulatory requirements for the new build have been addressed according to the filing record.

Ownership and Design

Fikes Wholesale, INC. is the owner and developer of record for this location. Interplan Architects, INC. served as the design firm of record. James A Gee is the registered accessibility specialist associated with the project. This is part of a broader portfolio for Fikes Wholesale, which has five other TDLR-registered projects totaling $4,361,400. These other locations are in Decatur, Longview, Post, Waco, and Little River Academy, all of which are also closed.

Interplan Architects has six other TDLR-registered projects totaling $3,402,350. These include locations in Webster, Houston, and other areas, with various statuses such as review complete or inspection complete. The design firm’s experience spans different project types, including convenience stores and office buildings.

Local Context and Comparison

According to U.S. Census American Community Survey 2023 five-year estimates for ZIP 75708, the population is about 10,001, with a median household income of $81,500. The median owner-occupied home value is $131,100, and housing is predominantly owner-occupied. There are 3,585 housing units in the area.

Comparing this project to 941 TDLR-registered new construction filings in Smith County, the estimated cost of $832,600 is close to the county median of $832,600. The size of 6,000 square feet is close to the median of 6,059 square feet. The cost per square foot of $139 is close to the county median of $162. The scheduled build window of 454 days is longer than the county median of 214 days. The Smith County unemployment rate was 4.4 percent in July 2026, higher than a year earlier.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75708 (Tyler)

One email per change. Unsubscribe in one click. Privacy.

CEFCO CONVENIENCE STORES # 1112 is a New Construction project located at 677 E. NORTHEAST LOOP 323 AT F M 14, Tyler, TX 75708 in Tyler, Texas. The project has an estimated value of $833K covering 6,000 sq ft. FIKES WHOLESALE, INC. is the property owner and INTERPLAN ARCHITECTS, INC. is the design firm of record. The project was registered with TDLR on September 13, 2021.

Frequently Asked Questions

Is the Cefco gas station in Tyler open?

The TDLR record shows the project file was closed in May 2023. This confirms the construction and accessibility review process is complete, but it does not confirm current business operating hours or status.

Who owns the Cefco store at 677 E. Northeast Loop 323?

Fikes Wholesale, INC. is the owner and developer of record. Interplan Architects, INC. was the design firm, and James A Gee is the registered accessibility specialist.

How much did it cost to build this gas station?

The estimated cost for the new construction was $832,600. This translates to $139 per square foot for the 6,000-square-foot facility.

When was the construction completed?

Construction started in February 2022. The completion date on the filing was May 2023, and the TDLR closed the project file in May 2023.

What is CEFCO CONVENIENCE STORES # 1112?

CEFCO CONVENIENCE STORES # 1112 is a new construction project at 677 E. NORTHEAST LOOP 323 AT F M 14 in Tyler, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: NEW GAS STATION

Is CEFCO CONVENIENCE STORES # 1112 open in Tyler?

Construction on CEFCO CONVENIENCE STORES # 1112 is complete — TDLR records show the project passed its required accessibility inspection in May 2023. The building is finished and very likely open.

Where is CEFCO CONVENIENCE STORES # 1112 located?

CEFCO CONVENIENCE STORES # 1112 is located at 677 E. NORTHEAST LOOP 323 AT F M 14, Tyler, TX, 75708, in Smith County.

Who is the owner or developer of CEFCO CONVENIENCE STORES # 1112?

FIKES WHOLESALE, INC. is the property owner/developer of record for CEFCO CONVENIENCE STORES # 1112, per its TDLR project registration.

Who is the architect or design firm for CEFCO CONVENIENCE STORES # 1112?

INTERPLAN ARCHITECTS, INC. is the design firm of record for CEFCO CONVENIENCE STORES # 1112, according to its TDLR filing.

How much does CEFCO CONVENIENCE STORES # 1112 cost and how big is it?

CEFCO CONVENIENCE STORES # 1112 has an estimated construction value of $833K and approximately 6,000 square feet (about $139/sqft), based on its TDLR filing.

Scope of Work

NEW GAS STATION

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

677 E. NORTHEAST LOOP 323 AT F M 14, Tyler, TX, 75708

Location by street address

Watch all construction in 75708 (Tyler)