โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Wichita Falls ISD | WF Legacy High School

3003 Henry S Grace Freeway, Wichita Falls, TX 76302, Wichita Falls, TX, 76302
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022000986
$118.8M
Project Value
376,831
Square Feet
$315/sqft
Cost/SqFt
2y 8mo
Duration
Registered:Sep 15, 2021
Start:Oct 25, 2021
Target:May 27, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

A new Wichita Falls Legacy High School for Wichita Falls ISD.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 15, 2021
Inspection Complete
May 27, 2024
Construction Start
October 25, 2021
Expected Completion
May 27, 2024

Get alerts for Wichita

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists