FM 730

From: 3.331 MI N of SH 114 To: SH 114 in Boyd, Boyd, TX 76023, Boyd, TX, 76023
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022011933
$32.0M
Project Value
2,407,996
Square Feet
$13/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Feb 16, 2022
Start:Dec 1, 2022
Target:Jul 31, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

For the reconstruction and widening of existing roadway and replacement of bridge and culvert structures consisting of grading, drainage, concrete and asphalt pavements, base, retaining walls, signs, markings, MBGF and delineation.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 16, 2022
Construction Start
December 1, 2022
Expected Completion
July 31, 2024