Traffic Signal Improvements (CSJ: 0902-90-283)

Berry St at New York Ave and Village Creek Rd, Fort Worth, TX, 76110

Opening ~Sep 2027Review Complete

Traffic Signal Improvements (CSJ: 0902-90-283) is a renovation/alteration project at Berry St at New York Ave and Village Creek Rd, Fort Worth, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Sep 2027. The project has an estimated value of $59K across about 2,106 sq ft.

Estimated project value
$59K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
2,106 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$28/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 29, 2026519 days across supplied datesSep 30, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    113 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    41 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    365 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Traffic Signal Improvements (CSJ: 0902-90-283)

TxDOT District: Fort Worth is executing a traffic signal improvement project at the intersection of Berry St and New York Ave, extending to Village Creek Rd in Fort Worth. The filing, identified by Csj: 0902-90-283, describes a renovation and alteration scope that includes installing new traffic signals, adding safety lighting, improving pedestrian signals, resurfacing the pavement, and adding a left turn lane and a right turn lane. The total estimated cost for this public roadway work is $59,381.

The project covers 2,106 sq ft of roadway area, resulting in a computed cost of $28 per square foot. This figure is below the county median of $79 per square foot for similar renovation and alteration filings in Tarrant County. While the total cost is in the bottom quarter of the 15,977 comparable filings in the county, the scheduled build window of 365 days is longer than the county median of 92 days.

Project Timeline and Status

The project was registered with TDLR in April 2026. Plan review was completed in August 2026, and the TDLR status is marked as Review Complete. Construction is scheduled to start in September 2026 and is scheduled to finish in September 2027. This one-year build window reflects the complexity of coordinating traffic signal installation and lane additions at an active intersection.

Frank Fonseca is listed as the registered accessibility specialist for this project. The work involves public funds and public land, consistent with its status as a Federally funded roadway project under TxDOT. TxDOT District: Fort Worth has six other TDLR-registered projects totaling $7,036,359, including projects in Fort Worth and Weatherford. This project is one of several ongoing infrastructure improvements in the region.

The intersection is located in ZIP code 76110, which has a population of about 33,640 people according to U.S. Census ACS 2022 five-year estimates. The median household income in this area is $59,933, and the median owner-occupied home value is $219,400. The housing stock is mostly owner-occupied, with 12,722 housing units recorded in the area.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76110 (Fort Worth)

One email per change. Unsubscribe in one click. Privacy.

Traffic Signal Improvements (CSJ: 0902-90-283) is a Renovation/Alteration project located at Berry St at New York Ave and Village Creek Rd, Fort Worth, TX 76110 in Fort Worth, Texas. The project has an estimated value of $59K covering 2,106 sq ft. TxDOT District: Fort Worth is the property owner. The project was registered with TDLR on April 29, 2026.

Frequently Asked Questions

What is the scope of work for this project?

The scope includes installing traffic signals, adding safety lighting, improving pedestrian signals, resurfacing the pavement, and adding a left turn lane and a right turn lane at the Berry St and New York Ave intersection.

Who is the owner of record?

The owner of record is TxDOT District: Fort Worth. The project is identified by Csj: 0902-90-283 and is a Federally funded roadway project involving public funds and public land.

When is construction scheduled to finish?

Construction is scheduled to start in September 2026 and is scheduled to finish in September 2027. Plan review was completed in August 2026, and the TDLR status is Review Complete.

What is the estimated cost of the project?

The estimated cost is $59,381 for 2,106 sq ft of work. This results in a computed cost of $28 per square foot, which is below the Tarrant County median of $79 per square foot for similar filings.

Is the business open?

The TDLR record only documents construction status. The project is scheduled to finish in September 2027. There is no information in the filing about a business opening or operating status.

What is Traffic Signal Improvements (CSJ: 0902-90-283)?

Traffic Signal Improvements (CSJ: 0902-90-283) is a renovation/alteration project at Berry St at New York Ave and Village Creek Rd in Fort Worth, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Install traffic signal, safety lighting, improve pedestrian signal, resurfacing, add left lane and right turn lane.

Is Traffic Signal Improvements (CSJ: 0902-90-283) open in Fort Worth?

Traffic Signal Improvements (CSJ: 0902-90-283) is still under construction in Fort Worth, TX, with an estimated completion of Sep 2027 according to its TDLR registration.

Where is Traffic Signal Improvements (CSJ: 0902-90-283) located?

Traffic Signal Improvements (CSJ: 0902-90-283) is located at Berry St at New York Ave and Village Creek Rd, Fort Worth, TX, 76110, in Tarrant County.

Who is the owner or developer of Traffic Signal Improvements (CSJ: 0902-90-283)?

TxDOT District: Fort Worth is the property owner/developer of record for Traffic Signal Improvements (CSJ: 0902-90-283), per its TDLR project registration.

How much does Traffic Signal Improvements (CSJ: 0902-90-283) cost and how big is it?

Traffic Signal Improvements (CSJ: 0902-90-283) has an estimated construction value of $59K and approximately 2,106 square feet (about $28/sqft), based on its TDLR filing.

Scope of Work

Install traffic signal, safety lighting, improve pedestrian signal, resurfacing, add left lane and right turn lane.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Berry St at New York Ave and Village Creek Rd, Fort Worth, TX, 76110

Location by street address

Watch all construction in 76110 (Fort Worth)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Fort Worth?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.