Funding type
This project involves public funds, public land, or is a Federally funded roadway project.
Traffic Signal Improvements (CSJ: 0014-01-032)
BU 287 at 29th St, Fort Worth, TX, 76133
Traffic Signal Improvements (CSJ: 0014-01-032) is a new construction project at BU 287 at 29th St, Fort Worth, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Jun 2028. The project has an estimated value of $95K across about 843 sq ft.
- Estimated project value
- $95K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 843 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $112/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 1 year
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
113 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
314 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
365 days after the preceding date shown.
Source: TDLR filing
View source record
📰About Traffic Signal Improvements (CSJ: 0014-01-032)
TxDOT District: Fort Worth is installing new traffic signals, ADA curb ramps, and safety lighting at the intersection of BU 287 and 29th St in Fort Worth. The project, filed as Traffic Signal Improvements (CSJ: 0014-01-032), is a new construction effort with an estimated cost of $94,640. This work focuses on improving pedestrian safety and accessibility at this specific roadway location in Tarrant County.
The scope of work includes installing traffic signals, APS push buttons, safety lighting, ADA curb ramps, pavement markings, and crosswalks. These improvements are designed to meet accessibility standards for pedestrians using the crosswalks. The project covers an area of 843 sq ft, resulting in a computed cost of $112 per square foot. This figure is close to the county median of $120 per square foot for similar new construction filings in Tarrant County.
Timeline and Status
The project was registered with TDLR in April 2026. Plan review was completed in August 2026. Construction is scheduled to start in June 2027. The filing indicates the project is scheduled to finish in June 2028. This represents a scheduled build window of 365 days, which is longer than the county median of 214 days for new construction projects of this type.
The estimated cost of $94,640 is below the county median of $800,000 for new construction filings in Tarrant County. This places the project in the bottom quarter of costs for this category. The funding source involves public funds, public land, or a Federally funded roadway project. The registered accessibility specialist for this filing is Frank Fonseca.
TxDOT District: Fort Worth has six other TDLR-registered projects totaling $7,001,100. These include projects in Fort Worth and Weatherford with various statuses ranging from registered to review complete. The area profile for ZIP 76133 indicates a population of about 53,825 and a median household income of $71,722, according to U.S. Census ACS 2023 five-year estimates. Housing in this area is mostly owner-occupied, with a median owner-occupied home value of $223,200.
Review Complete
Design review complete, construction may proceed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 76133 (Fort Worth)
One email per change. Unsubscribe in one click. Privacy.
Traffic Signal Improvements (CSJ: 0014-01-032) is a New Construction project located at BU 287 at 29th St, Fort Worth, TX 76133 in Fort Worth, Texas. The project has an estimated value of $95K covering 843 sq ft. TxDOT District: Fort Worth is the property owner. The project was registered with TDLR on April 29, 2026.
Frequently Asked Questions
What is the current status of the traffic signal installation?
TDLR completed plan review in August 2026. Construction is scheduled to start in June 2027 and is scheduled to finish in June 2028. The project is in the pre-construction phase.
How much does the project cost?
The estimated cost for the Traffic Signal Improvements project is $94,640. This amount is below the county median for new construction filings in Tarrant County.
Who is the owner of the project?
The owner of record is TxDOT District: Fort Worth. The project is located at BU 287 at 29th St in Fort Worth, TX.
What specific improvements are included in the scope?
The scope includes installing traffic signals, APS push buttons, safety lighting, ADA curb ramps, pavement markings, and crosswalks. These improvements aim to enhance safety and accessibility for pedestrians.
What is Traffic Signal Improvements (CSJ: 0014-01-032)?
Traffic Signal Improvements (CSJ: 0014-01-032) is a new construction project at BU 287 at 29th St in Fort Worth, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Install traffic signals, APS push buttons, safety lighting, ADA curb ramps, pavement markings and crosswalks.
Is Traffic Signal Improvements (CSJ: 0014-01-032) open in Fort Worth?
Traffic Signal Improvements (CSJ: 0014-01-032) is still under construction in Fort Worth, TX, with an estimated completion of Jun 2028 according to its TDLR registration.
Where is Traffic Signal Improvements (CSJ: 0014-01-032) located?
Traffic Signal Improvements (CSJ: 0014-01-032) is located at BU 287 at 29th St, Fort Worth, TX, 76133, in Tarrant County.
Who is the owner or developer of Traffic Signal Improvements (CSJ: 0014-01-032)?
TxDOT District: Fort Worth is the property owner/developer of record for Traffic Signal Improvements (CSJ: 0014-01-032), per its TDLR project registration.
How much does Traffic Signal Improvements (CSJ: 0014-01-032) cost and how big is it?
Traffic Signal Improvements (CSJ: 0014-01-032) has an estimated construction value of $95K and approximately 843 square feet (about $112/sqft), based on its TDLR filing.
Scope of Work
Install traffic signals, APS push buttons, safety lighting, ADA curb ramps, pavement markings and crosswalks.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
BU 287 at 29th St, Fort Worth, TX, 76133
Watch all construction in 76133 (Fort Worth)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Fort Worth?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.