๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Greater St. Stephen Missionary Baptist Church

1305 Clifton St, Waco, TX 76704, Waco, TX, 76704
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022011948
$980K
Project Value
8,608
Square Feet
$114/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Feb 17, 2022
Start:Apr 30, 2022
Target:Dec 31, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Church with fellowship hall, classrooms, kitchen, rest rooms, offices and parking lot.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 17, 2022
Construction Start
April 30, 2022
Expected Completion
December 31, 2023