๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Hampton Manor of Crowley
1000 Canoe Way, Crowley, TX 76036, Crowley, TX, 76036
Construction50%
๐Project Metrics
TDLR #TABS2022013369$7.0M
Project Value
66,592
Square Feet
$105/sqft
Cost/SqFt
9 months
Duration
Registered:Mar 6, 2022
Start:Mar 27, 2022
Target:Dec 15, 2022
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction pf a new assisted living facility
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 6, 2022
Construction Start
March 27, 2022
Expected Completion
December 15, 2022
๐Related Projects
๐๏ธSame Design Firm
$7.8M totalProperty Owner
๐ค
INVESTORS LAND HOLDINGS OF CROWLEY
Contact: Shahid Imran
View company profile
7560 River Rd., Flushing, Michigan 48433
Design Firm
๐๏ธ
ARTEC INTEGRATED SOLUTIONS
4 projects ยท $7.8M
View company profile
4100 Spring Valley Suite 465, Dallas, Texas 75244