๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Methodist Hospital Electrical Infrastructure Upgrade

7700 Floyd Curl Drive, San Antonio, TX 78229, San Antonio, TX, 78229
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022013702
$823K
Project Value
7,790
Square Feet
$106/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Mar 9, 2022
Start:Apr 1, 2022
Target:Jun 1, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

The scope of work routes electrical conduit through the existing hospital from Sublevel 2 up to the 5th Floor. An electrical room will be added on Sublevel 2. Minor renovation will take place in two single occupant restrooms to allow for conduit run

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 9, 2022
Construction Start
April 1, 2022
Expected Completion
June 1, 2023