๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SH 16

From: LP 1604 To: 0.3 mi W of FM 1560 (Leslie Rd), San Antonio, TX 78229, San Antonio, TX, 78229
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022014628
$12.7M
Project Value
48,866
Square Feet
$260/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Mar 22, 2022
Start:Jul 1, 2022
Target:Jun 1, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Intersection and operational improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 22, 2022
Construction Start
July 1, 2022
Expected Completion
June 1, 2024