New Hemphill ISD Middle School Classrooms & Offices

1000 Milan Street, Hemphill, TX 75948, Hemphill, TX, 75948
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022015707
$3.8M
Project Value
19,050
Square Feet
$199/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Apr 4, 2022
Start:Jun 1, 2022
Target:Dec 30, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Renovation of existing Middle Scholl and addition of new classrooms, restrooms, and administrative offices

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 4, 2022
Construction Start
June 1, 2022
Expected Completion
December 30, 2023